NGTL Abandonment Program (2021)
NGTL is proposing to permanently cease operations at 10 meter stations and 11 associated lateral pipelines, four stand-alone meter stations, and two stand-alone laterals on the NGTL System within Alberta because these facilities are no longer necessary to provide service to customers. The CER defines this process as abandonment. As operations will be permanently ceased and service will be discontinued on these facilities, NGTL will file a Section 241(1) application, pursuant to the Canadian Energy Regulator Act, for the facilities. Please view the Abandonment factsheet for more information.
Program timeline
Q2 2021 |
Began evaluation of site-specific risks at the proposed sites |
Q4 2021 |
Begin Indigenous and stakeholder engagement with impacted landowners and Indigenous communities |
Q2 2022 |
Anticipate filing a Section 241 Abandonment application with the CER |
Q3 2023 |
Subject to regulatory approval, program activities will begin at select sites |
Program Schedule
Program activities will begin in Q3 2023 at select sites and continue through Q4 2024. Please note, schedules are subject to change and will be updated and communicated to stakeholders accordingly.
View the program schedule
Facility/Pipeline Name |
Start/Finish Dates |
Duration |
---|---|---|
Valhalla Sales |
Aug 1, 2023 – Aug 17, 2023 |
17 days |
Valhalla Sales Lateral (NPS 2 1987) |
Aug 1, 2023 – Aug 28, 2023 |
28 days |
Winefred River West |
Dec 1, 2023 – Dec 21, 2023 |
21 days |
Russell Creek |
Dec 1, 2024 – Dec 28, 2024 |
28 days |
Chester Creek Receipt MS |
Dec 1, 2024 – Dec 30, 2024 |
30 days |
Keppler Creek |
Dec 1, 2024 – Dec 30, 2024 |
30 days |
Bison Lake Receipt MS |
Dec 1, 2024 – Dec 30, 2024 |
30 days |
Rambling Creek Receipt |
Dec 1, 2024 – Dec 30, 2024 |
30 days |
Russell Creek Sales |
Dec 1, 2024 – Dec 30, 2024 |
30 days |
Russell Creek Lateral (NPS 10 1994) |
Dec 1, 2024 – Jan 9, 2025 |
40 days |
Bison Lake Lateral (NPS 12 1994) |
Dec 1, 2024 – Jan 13, 2025 |
44 days |
Rambling Creek Lateral |
Dec 1, 2024 – Jan 13, 2025 |
44 days |
Tweedie South Lateral (NPS 4 1975) |
Jul 1, 2023 – Nov 1, 2023 |
124 days |
Tweedie South |
Jul 1, 2023 – Nov 1, 2023 |
124 days |
Wolverine River |
Jan 2, 2024 – Jan 31, 2024 |
30 days |
Sakwatamau River Sales |
Nov 2, 2023 – Nov 18, 2023 |
17 days |
Sakwatamau River Sales Lateral (NPS 6 1989) |
Nov 2, 2023 – Nov 29, 2023 |
28 days |
Calais Receipt MS |
Oct 2, 2023 – Oct 29, 2023 |
28 days |
Countess West RMS |
Sept 5, 2023 – Sept 22, 2023 |
12 days |
Countess West Lateral |
Sept 5, 2023 – Sept 26, 2023 |
16 days |
Virginia Hills Sales #2 |
Nov 6, 2023 – Nov 22, 2023 |
17 days |
Virginia Hills |
Nov 6, 2023 – Nov 22, 2023 |
17 days |
Virginia Hills Lateral (NPS 8 1970) |
Nov 6, 2023 – Dec 3, 2023 |
28 days |
Winefred River West Lateral |
Jan 15, 2024 – Feb 13, 2024 |
30 days |
Wiau Lake South Lateral |
Jul 16, 2023 – Nov 1, 2023 |
109 days |
Wiau Lake South |
Jul 16, 2023 – Nov 1, 2023 |
109 days |
Wayne North Lateral (NPS 6 1959) |
Oct 17, 2023 – Nov 29, 2023 |
32 days |
Cessford East Lateral (NPS 8 1960) |
Sept 26, 2023 – Oct 18, 2023 |
17 days |
Documents and maps
Regulatory
How are we regulated?
The proposed Project will be conducted on part of the NGTL System, which is regulated by the CER.
Regulatory contact
Canada Energy Regulator (CER) | ||
---|---|---|
Local | 1-403-292-4800 | 1-403-292-5503 |
Toll-Free | 1-800-899-1265 | 1-877-288-8803 |
Ways to reach us
If you have any questions about the Project, please reach out to us via the contact information below.
Landowner Helpline | |
---|---|
A key component in maintaining the integrity of our facilities is input from all stakeholders: Indigenous communities, landowners and governments. If you have questions or concerns, please let us know. | |
Head Office |
1-866-372-1601 |
Media Relations | |
---|---|
TC Energy welcomes enquiries from media. Please direct questions to: | |
1-800-608-7859 Toll-free (North America) | media@tcenergy.com |
Investor Relations | |
---|---|
We welcome inquiries from analysts, shareholders and prospective shareholders at: | |
1-800-361-6522 Toll-free (North America) | investor_relations@tcenergy.com |