NGTL Abandonment Program (2021)

NGTL is proposing to permanently cease operations at 10 meter stations and 11 associated lateral pipelines, four stand-alone meter stations, and two stand-alone laterals on the NGTL System within Alberta because these facilities are no longer necessary to provide service to customers. The CER defines this process as abandonment. As operations will be permanently ceased and service will be discontinued on these facilities, NGTL will file a Section 241(1) application, pursuant to the Canadian Energy Regulator Act, for the facilities. Please view the Abandonment factsheet for more information.

Program timeline

Q2 2021

Began evaluation of site-specific risks at the proposed sites

Q4 2021

Begin Indigenous and stakeholder engagement with impacted landowners and Indigenous communities

Q2 2022

Anticipate filing a Section 241 Abandonment application with the CER

Q3 2023

Subject to regulatory approval, program activities will begin at select sites

Program Schedule

Program activities will begin in Q3 2023 at select sites and continue through Q4 2024. Please note, schedules are subject to change and will be updated and communicated to stakeholders accordingly.

Facility/Pipeline Name

Start/Finish Dates

Duration

Valhalla Sales

Aug 1, 2023 – Aug 17, 2023

17 days

Valhalla Sales Lateral (NPS 2 1987)

Aug 1, 2023 – Aug 28, 2023

28 days

Winefred River West

Dec 1, 2023 – Dec 21, 2023

21 days

Russell Creek

Dec 1, 2024 – Dec 28, 2024

28 days

Chester Creek Receipt MS

Dec 1, 2024 – Dec 30, 2024

30 days

Keppler Creek

Dec 1, 2024 – Dec 30, 2024

30 days

Bison Lake Receipt MS

Dec 1, 2024 – Dec 30, 2024

30 days

Rambling Creek Receipt

Dec 1, 2024 – Dec 30, 2024

30 days

Russell Creek Sales

Dec 1, 2024 – Dec 30, 2024

30 days

Russell Creek Lateral (NPS 10 1994)

Dec 1, 2024 – Jan 9, 2025

40 days

Bison Lake Lateral (NPS 12 1994)

Dec 1, 2024 – Jan 13, 2025

44 days

Rambling Creek Lateral

Dec 1, 2024 – Jan 13, 2025

44 days

Tweedie South Lateral (NPS 4 1975)

Jul 1, 2023 – Nov 1, 2023

124 days

Tweedie South

Jul 1, 2023 – Nov 1, 2023

124 days

Wolverine River

Jan 2, 2024 – Jan 31, 2024

30 days

Sakwatamau River Sales

Nov 2, 2023 – Nov 18, 2023

17 days

Sakwatamau River Sales Lateral (NPS 6 1989)

Nov 2, 2023 – Nov 29, 2023

28 days

Calais Receipt MS

Oct 2, 2023 – Oct 29, 2023

28 days

Countess West RMS

Sept 5, 2023 – Sept 22, 2023

12 days

Countess West Lateral

Sept 5, 2023 – Sept 26, 2023

16 days

Virginia Hills Sales #2

Nov 6, 2023 – Nov 22, 2023

17 days

Virginia Hills

Nov 6, 2023 – Nov 22, 2023

17 days

Virginia Hills Lateral (NPS 8 1970)

Nov 6, 2023 – Dec 3, 2023

28 days

Winefred River West Lateral

Jan 15, 2024 – Feb 13, 2024

30 days

Wiau Lake South Lateral

Jul 16, 2023 – Nov 1, 2023

109 days

Wiau Lake South

Jul 16, 2023 – Nov 1, 2023

109 days

Wayne North Lateral (NPS 6 1959)

Oct 17, 2023 – Nov 29, 2023

32 days

Cessford East Lateral (NPS 8 1960)

Sept 26, 2023 – Oct 18, 2023

17 days

Regulatory

How are we regulated?

The proposed Project will be conducted on part of the NGTL System, which is regulated by the CER.

Regulatory contact
Canada Energy Regulator (CER)
Local 1-403-292-4800 1-403-292-5503
Toll-Free 1-800-899-1265 1-877-288-8803

Ways to reach us

If you have any questions about the Project, please reach out to us via the contact information below. 

Landowner Helpline
A key component in maintaining the integrity of our facilities is input from all stakeholders: Indigenous communities, landowners and governments. If you have questions or concerns, please let us know.

Head Office
450 – 1 St. SW
Calgary, Alberta
T2P 5H1

1-866-372-1601

Media Relations
TC Energy welcomes enquiries from media. Please direct questions to:
1-800-608-7859 Toll-free (North America)

Investor Relations
We welcome inquiries from analysts, shareholders and prospective shareholders at: 
1-800-361-6522 Toll-free (North America)