Saddle Lake Lateral Loop Project

Natural Gas Icon

Overview 

NOVA Gas Transmission Ltd. (NGTL), a wholly owned subsidiary of TransCanada PipeLines Limited, an affiliate of TC Energy Corporation, will construct, own and operate the Saddle Lake Lateral Loop (Cold Lake Section) Project. This project is required to connect growing natural gas production in Alberta and increase the delivery capability to growing market demand in northeast Alberta and northwest Saskatchewan.

Located entirely within the Municipal District of Bonnyville, the pipeline route will parallel an existing pipeline, and consists of 20 kilometre (km) of 20-inch pipe, south of the City of Cold Lake, Alberta, connecting to the existing NGTL System. As part of the project, the existing Cold Lake Border Sales metering facility will be replaced with a new metering facility to accommodate the additional gas volumes.

Once the new pipeline and meter station become operational, gas supply through a 20 km portion of the existing pipeline will be discontinued. This section of pipe, and two existing meter stations along this segment, will then be decommissioned.

On July 17, 2020, NGTL received approval from the Canada Energy Regulator (CER) to construct and decommission the Project. Construction will begin in October 2020 with an anticipated in-service date of November 1, 2021. Decommissioning activities are anticipated to begin following in-service of the Project. The Project will also use a horizontal directional drill under the Beaver River.

Learn more about how we safely cross bodies of water

Project status and timelines

 

Q3 2018

Began Indigenous and stakeholder consultation

Q3 2018

Commenced survey and field studies

Q3 2019

Filed a joint section 58 and section 45.1 application pursuant to the National Energy Board Act (predecessor to the Canada Energy Regulator) and National Energy Board Onshore Pipeline Regulations

Q4 2020

Commence construction activities

Q2 2021

Anticipated in-service date

Community benefits

The Project will offer short-term and long-term economic benefits and help strengthen the economy on a local, provincial and national level.

Employment opportunities – Construction will require the services of equipment operators, welders, mechanics, truck drivers, labourers and more.

Business opportunities – Pipeline construction will create demand for local goods and services including food and accommodation, hardware, industrial parts, automotive parts and servicing, fuel and more.

Annual revenue to support local services – Project construction will result in tax payments to municipal, provincial and federal governments. When the Project is operational, annual tax payments will help support schools and hospitals, emergency services, recreation facilities, recycling programs and other local programs vital to sustaining communities.

Investment in local communities – Through our engagement with people in the areas we work, we will identify areas where we can help build stronger, safer and more vibrant communities through local partnerships and initiatives.

Documents and maps

The Saddle Lake Lateral Loop (Cold Lake Section) Project is required to connect growing natural gas production in Alberta and increase the delivery capability to growing market demand in northeast Alberta and northwest Saskatchewan.

Regulatory documents

How are we regulated?

The Saddle Lake Lateral Loop Project is governed according to regulations outlined by the Canada Energy Regulator (CER), which replaced the National Energy Board (NEB) on August 28, 2019. For more information about the CER web site.

Regulatory contact

Canada Energy Regulator (CER)
Local 1-403-292-4800 1-403-292-5503
Toll-Free 1-800-899-1265 1-877-288-8803

WEBSITE EMAIL

Ways to reach us

We’re here to answer your questions. For general questions you can contact us by email, but for a quicker response, please call us directly.

Emergency Response
Our commitment to the safety of our people, pipelines and facilities is unwavering. In case of an emergency, please call the appropriate 24-hour toll-free hotline:
Canada: 1-888-982-7222

Landowner Helpline
A key component in maintaining the integrity of our facilities is input from all stakeholders: Indigenous communities, landowners and governments. If you have questions or concerns, please let us know.

Head Office
450 – 1 St. SW
Calgary, Alberta
T2P 5H1

1-866-372-1601

Media Relations
TC Energy welcomes enquiries from media. Please direct questions to:
1-800-608-7859 Toll-free (North America)

Investor Relations
We welcome inquiries from analysts, shareholders and prospective shareholders at:
1-800-361-6522 Toll-free (North America)

Public Affairs
We welcome inquiries from stakeholders at:
1-855-895-8754 Toll-free (North America)