1. EN
  2. FR
  3. ES

West Path Delivery 2022 Projects

West Path Delivery 2022 Scope

The scope for West Path Delivery Program in 2022 included the Foothills Zone 8 West Path Delivery 2022 Project and the NGTL West Path Delivery 2022 Project. These projects consisted of approximately 36 km of 48-inch diameter (NPS 48) pipeline expansions and a meter station expansion and were placed in-service between Q4 2022 / Q1 2023.

NGTL West Path Delivery 2022

  • The Edson Mainline Loop 4 Raven River Section is approximately 18 km of 48-inch diameter (NPS 48) pipeline within the Province of Alberta. The pipeline is located approximately 16 km northwest of the Town of Sundre, AB.
  • The Western Alberta System Mainline Loop 2 (WASML) Alberta British Columbia Section is approximately 5 km of 48-inch diameter (NPS 48) pipeline within the Province of Alberta. The pipeline is located approximately 6 km west of Coleman, AB. 
  • The Alberta British Columbia (ABC) Border Meter Station Expansion is located approximately 6 km west of Coleman, AB. 
  • NGTL filed an application with the Canada Energy Regulator (CER) under Section 214 of the Canadian Energy Regulator Act on June 1, 2020. On April 30, 2021, NGTL received the necessary Project approvals from the CER to proceed with construction.

View the NGTL West Path Delivery 2022 Project Fact Sheet

Foothills Zone 8 West Path Delivery 2022

  • The British Columbia Mainline Loop 2 Yahk Section is approximately 13 km of 48-inch diameter (NPS 48) pipeline within the Province of British Columbia. The pipeline is located approximately 25 km east of the Town of Creston, B.C.
  • Foothills filed an application with the CER under Section 214 of the Canadian Energy Regulator Act on June 2, 2020. On October 28, 2020, Foothills received the necessary Project approvals from the CER to proceed with construction.

View the Foothills Zone 8 West Path Delivery Project Fact Sheet

 

Project schedule

 

Q3 2019

Commenced environmental & technical analysis

Q3 2019

Commenced survey & field studies

Q4 2019

Began broad engagement on project study areas

Q4 2019

Foothills Zone 8 West Path Delivery 2022 Project commenced landowner engagement

Q4 2019

NGTL West Path Delivery 2022 Project commenced landowner engagement

Q4 2019

Commenced early Indigenous and stakeholder engagement

Q1 2020

Filed Project Notifications with the CER

Q2 2020

Filed applications with the CER

Q4 2020

Foothills Zone 8 West Path Delivery 2022 Project approved by the CER

Q2 2021

NGTL Westh Path Delivery 2022 Project approved by the CER

Q1 2022

Commenced clearing activities on:

  • NGTL West Path Delivery 2022 Project - Edson Mainline Loop 4 Raven River Section
  • NGTL West Path Delivery 2022 Project – WASML 2 Alberta British Columbia Section 
  • Foothills Zone 8 West Path Delivery 2022 Project - British Columbia Mainline Loop 2 Yahk Section
Q2/Q3 2022

Commenced mainline construction activities on:

  • Foothills Zone 8 West Path Delivery 2022 Project – British Columbia Mainline Loop 2 Yahk Section
  • NGTL West Path Delivery 2022 Project - Edson Mainline Loop 4 Raven River Section
  • NGTL West Path Delivery 2022 Project – WASML 2 Alberta British Columbia Section

Commenced and completed meter station construction activities on the NGTL West Path Delivery 2022 Project – ABC Border Meter Station Expansion

Q4 2022 / Q1 2023

Construction completed and all project components placed into service

FAQs

Our Commitment

Regulatory

The Projects are governed according to regulations by the Canada Energy Regulator (CER).

Regulatory Information

NGTL filed a Project Notification for the NGTL West Path Delivery 2022 Project with the CER in Q1 2020. On June 1, 2020, NGTL filed an application with the CER under Section 214. On April 30, 2021, NGTL received the necessary Project approvals from the CER to proceed with construction.

Foothills filed a Project Notification for the Foothills Zone 8 West Path Delivery 2022 Project with the CER in Q1 2020. On June 2, 2020, Foothills filed an application with the CER under Section 214 of the Canadian Energy Regulator Act. On October 28, 2020, Foothills received the necessary Project approvals from the CER to proceed with construction. 

Ways to reach us

We’re here to answer your questions. For general questions you can contact us by email, but for a quicker response, please call us directly. Visit our overview page for a full list of contacts.