Station 802 C1 Unit Addition

Natural Gas Icon

Overview 

TransCanada PipeLines Limited (TCPL) applied to the National Energy Board (NEB), predecessor to the Canada Energy Regulator (CER), for an order approving the construction and operation of the Station 802 C1 Unit Addition, located in the municipality of Saint-Phillippe, Québec.

This Project is part of the TQM Reinforcement Program that encompasses a joint facility planning effort between Trans Québec & Maritimes Pipeline Inc. (TQM), Énergir, L.P. (Énergir), and TCPL. More information about this Program is available on the TQM site.

The TQM Reinforcement Program will result in an increase in flow of natural gas through Station 802, thereby increasing the required compression power at site. The purpose and scope of this Project is to add an additional compressor unit at Station 802 to ensure contractual demand obligations continue to be met. The anticipated in-service date for the facility is November 2022.

Project Schedule

Q3 2018

TC Energy begins engagement with stakeholders

Q3 2018

Environmental and technical analyses begin

Q3 2019

An application to build the pipeline is filed with the NEB under section 58

Q3 2021

Subject to regulatory approvals, construction should begin

Q3/Q4 2022

Projected completion date

 

Regulatory

 

Regulatory documents

On August 23, 2019, TCPL filed a section 58 application with the National Energy Board (NEB), predecessor to the Canada Energy Regulator (CER) for its proposed Station 802 C1 Unit Addition project.

To view the French version of the application, select the document link listed below.

Pour consulter la version française de la demande, sélectionnez le lien vers le document ci-dessous.

Regulatory contacts

The Station 802 C1 Unit Addition project is governed according to regulations outlined by the Canada Energy Regulator (CER).

Canada Energy Regulator (CER)
Local 1-403-292-4800 1-403-292-5503
Toll-Free 1-800-899-1265 1-877-288-8803

WEBSITE EMAIL

Ways to reach us

TC Energy is committed to notifying affected landowners, towns, communities and local, state and federal governments and agencies involved in the project. If you have any questions about the project, please reach out to us via the contact information below.

Project Station 802
Project Station 802 (TC Energy)
C.P. 34. St-Augustin-de-Desmaures, Québec
Canada, G3A 1V9
1-418-930-1559  caroline_beaudry@tcenergy.com

Emergency Response
Our commitment to the safety of our people, pipelines and facilities is unwavering, visit our Contact page for our complete list of emergency numbers.

Landowner Helpline
A key component in maintaining the integrity of our facilities is input from all stakeholders: Indigenous communities, landowners and governments. If you have questions or concerns, please let us know.

Head Office
450 – 1 St. SW
Calgary, Alberta
T2P 5H1

1-866-372-1601

Investor Relations
We welcome inquiries from analysts, shareholders and prospective shareholders at:
1-800-361-6522 Toll-free (North America)

Media Relations
TC Energy welcomes enquiries from media. Please direct questions to:
1-800-608-7859 Toll-free (North America)